Crux Subsurface, Inc. (Crux) has completed the second phase of work for Hawaiian Electric’s Koolau-Wailupe #1 and #2 46 kV Circuits in Oahu, Hawaii.

The second portion of the project involved installing an additional four micropile foundations for tubular steel pole structures. Crux was selected to perform additional services due to difficulty in accessing the foundation sites. Drilling activities took place while overhead lines were still in-service and crew members had to maintain high levels of communication with helicopter pilots during periods of strong winds, fog, and rain.

The first phase was completed in early January and included replacing nine wooden structures. Crux partnered with sister company Road Bore Corp. to provide foundation design and installation services for the project. Due to the rugged and steep terrain of the location, helicopter-support was utilized to transport crews and materials to each site.

Crux completed the project in early February and installed a total of 13 foundations.

 

Recommended Posts

Back to Index
Uncategorized
Crux Recognized as an ADSC Safety Award Winner

September 1, 2020 The International Association of Foundation Drilling (ADSC) has named Crux a Safety Award Winner for the calendar year 2019.  Crux is recognized in the 100,000-300,000...

Learn More
News
Crux Announces New President

January 13, 2020 Crux Subsurface, Inc. (Crux) is pleased to announce Scott Tunison as company President. Mr. Tunison co-founded Crux in 1998 and has seen the company through...

Learn More
News
Crux Participates in ISM 2019, Australia

August 23, 2019 Crux engineers were in Australia’s Gold Coast this week to present case studies and participate in expert panel discussions at the 14th International Workshop for...

Learn More
Copyright © 2021 Crux Subsurface, Inc.
Back to Top