Home Projects

Wood to Steel Replacement Segments

See all Projects
Project Details

Location: San Diego County

Project Description

San Diego Gas & Electric’s (SDG&E) Wood to Steel Replacement Program will replace approximately 5,500 existing wood transmission poles in San Diego County with tubular steel poles. The purpose of the program is to reduce maintenance expenses, improve fire safety, and reduce damage to SDG&E infrastructure during fire season.  The project is being completed in various segments over the course of several years.

Team Members

San Diego Gas & Electric, Crux Subsurface Inc., DCI Engineering, and FSR Engineering

Crux’s Role

Hard rock and close proximity to residential homes necessitated a foundation alternative to excavated or drilled shafts at a number of sites.  Crux was selected to provide design-build micropile foundations, typically for dead-end or angled structures.  Specialty compact equipment was used to successfully install foundations under energized lines and within six feet of existing wood poles.

To date, Crux has designed and installed 172 foundations on eight separate segments.  Access constraints and geotechnical conditions have varied significantly, requiring a combination of track vehicle, crane, and helicopter.  Crux’s customized micropile installation equipment can be broken into 2,500-pound components, allowing for more efficient transportation.  The drills can also operate with as little as 10 feet of overhead clearance, which was beneficial as extended power outages were not permitted.

Micropiles were installed in battered arrays of between 3 and 16 piles, depending on site-specific geotechnical conditions and tower loads.  Steel pile caps were installed on all but two foundations, which employed concrete pile caps.  The piles at these two locations needed to be spaced further than usual to bridge an underground utility, which would have resulted in steel caps too large and heavy to be feasible.  Steel caps were installed at the remaining 168 structure locations.  The caps were fabricated in a controlled, offsite facility and transported to the sites for installation.

Crux recently completed its largest scope of work on a Wood to Steel segment, installing 87 steel cap micropile foundations for SDG&E’s TL 637.  The project required close coordination with other SDG&E subcontractors, completing alignment sections out of sequence and erecting poles immediately following foundation completion.  Select foundation sites were located in protected habitats and required enhanced mitigation measures.  Upon completion of the project, Crux received a letter from the SDG&E Environmental Programs team expressing their gratitude at the extra effort put forth to avoid environmental impacts.

Completed Segments:
TL 678 (23 structures – 2010), TL 685 (32 structures – 2010), SP 820/821 (2 structures – 2010), TL 689 (20 structures – 2011), TL 6927 (2 structures – 2011), TL 635 (4 structures – 2011), TL 6913 (2 structures –2013), TL 637 (87 Structures – 2014)

 

 

Related Projects

Lolo-Oxbow 230 kV Transmission Line Rebuild

Micropile design and construction for four remote-access river crossing structures requiring an alternative foundation option.

View Project
Antimony to Burke A&B Transmission Rebuild

Project Description The Antimony to Burke project involved the rebuild of an approximately 13-mile 115 kV transmission line between Western Montana and Eastern Idaho.  The...

View Project
Paris to Ark City Transmission Line

Project Description The Paris to Ark City Transmission Line involved upgrading an existing power system originally built in the 1940’s and nearing the end of...

View Project
Copyright © 2021 Crux Subsurface, Inc.
Back to Top