Project Description

The Iowa Hill Pump Storage Project is a Sacramento Municipal Utility District (SMUD) project located in El Dorado County.  The proposed facility would pump water 1,200 feet uphill when power is available and let it flow downhill to generate electricity when needed.

Team Members

SMUD, Jacobs Associates, Carlton Engineering, Crux Subsurface, Inc.

Crux’s Role

Crux was selected to provide core drilling and sampling, insitu testing and instrumentation.  Two borings provided geotechnical data for the construction of an underground pump house, and a third provided information regarding rock quality at the proposed storage pond area.  Geotechnical conditions were challenging, but the sites allowed for access by track-mounted drill rig.

The first two borings were 10-degrees sub horizontal, and drilled to depths of 2,002 and 1,473 feet.  Packer testing and hydraulic fracturing were completed in both, and Crux performed optical borehole imaging (OBI) the full length of each hole.  Testing and OBI activities were challenging due to the poor soil conditions in the area.  Both borings successfully stayed within deviation requirements and reached their targets without the need for downhole corrections.

The third boring was vertical and drilled to 1,487 feet.  Packer testing and hydraulic fracturing were performed, and OBI was completed the full depth of the hole.  Upon the completion of imaging activities, Crux installed three permanent vibrating wire piezometer transducers at varying depths before grouting the hole.  Water inflow was experienced, requiring pressure grout using a nitrogen packer system at numerous intervals for successful abandonment.

 

 

Related Projects

Sunrise Powerlink Geotechnical

San Diego Gas and Electric (SDG&E) proposed a new 117-mile, high-voltage transmission line that will have a 1,000 megawatt capacity to transport renewable energy from...

View Project
US 89 Landslide

On February 20, 2013, a landslide occurred on U.S. 89 near Page, Arizona. More than 150 feet of roadway buckled causing the indefinite closure of...

View Project
Going to the Sun Road Rehabilitation

The Going-to-the-Sun Road in Glacier National Park was built in 1932, and is a narrow 52-mile paved highway. The National Park Service and Federal...

View Project
Copyright © 2021 Crux Subsurface, Inc.
Back to Top